Check out our awesome project schedule template (Gantt chart) for construction of a new 2-storey home with crawl space foundation.
FEATURES
- Template created in Microsoft Project 2007 and saved as .MPP file format
- Accounts for construction activities from Clear Lot through to Handover / Move-in
- Relationships between activities have been assigned
- The template is fully customizable
DESCRIPTION
You do not need to start from scratch. Activities have been identified with estimated duration and sequenced (activity relationship added). To get started you just need to review each activity, its duration and relationships to suit your specific project requirements.
The project tasks are sorted in the following phases:
- Project management
- Site preparation
- Footings & foundations
- Framing
- Exterior finishes
- Utility rough-ins
- Interior Finishes
- Insulation
- Drywall
- Finishes
- Utility
- Landscaping
- Final acceptance
STATISTICS
- # Project = 1
- # Activities = 68
- # Critical Activities = 47
- Project Duration 147 days
PLEASE READ BEFORE PURCHASING – The .MPP file format is for Microsoft Project 2007 or later.